Drawings to send
- Plumbing plans and riser diagrams
- Fixture schedules
- Plumbing specifications
Commercial plumbing quantities start with the fixture schedule, then measure pipe by system. Ten fixtures do not produce a pipe length.

Send plumbing plans, risers, the fixture schedule, and note whether underground piping and insulation are included.
Most estimates that include plumbing are delivered in 24–48 hours. Expect a fee that is typically $150–$1,000 per estimate, by project size and scope.
Domestic cold, hot, hot-return, sanitary, vent, and storm each get their own pipe runs by material and diameter. Lavatories and water closets stay on separate fixture rows because their carriers and trims differ. A teaching schedule of 6 lavatories and 4 water closets is 10 fixtures and still zero linear feet of pipe. Insulation, excavation, and medical gas are exclusions unless the specification assigns them here. The workbook records the sheet for every run.
These rows show how a commercial workbook can separate units. They are teaching lines, not a client bid and not a price.
| Line item | Unit or basis | Drawing reference | Review note |
|---|---|---|---|
| Lavatories | EA | Fixture schedule | Separate from water closets |
| Water closets | EA | Fixture schedule | Carriers noted if specified |
| Domestic water pipe | LF by diameter | Plans and risers | Cold, hot, and return stay apart |
| Sanitary and vent | LF by diameter | Waste riser | Storm is not added into sanitary |
A related teaching file is available: Plumbing takeoff worksheet. It is not a bid deliverable.
Separate domestic cold water, hot water, return, sanitary, vent and storm systems. Measure pipe by material, diameter and level; count fixtures against schedules and identify equipment connection kits separately.
Keep trenching, insulation, medical gas and utility work beyond the building connection distinct. Record whether fittings are counted individually or carried under a stated allowance.
Illustrative fixture schedule: 6 lavatories plus 4 water closets equals 10 fixtures, but water-supply and sanitary piping must be measured separately by diameter and linear foot.
Only if the bid form allows a lump fixture item. For a building estimate, fixture types stay split so carriers and connection kits are not missed.
Write it down. Underground pipe inside the building and civil utility work outside are easy to double-count or to drop.
Leave the run as an open question. Do not draw a pipe length that the documents do not support.
Inclusions, exclusions, and whether this trade is in your package are confirmed in the project quote. This page does not certify design or code compliance. PlanSwift and Bluebeam are named only as tools used in the industry.