Drawings to send
- Electrical plans and panel schedules
- Lighting fixture schedules
- Electrical specifications and addenda
Send the electrical drawings for an Excel takeoff organized by fixture type, branch devices, feeder raceways and equipment. The quote confirms whether you need quantities or priced scope.

Send electrical plans, the luminaire schedule, panel schedules, and say whether fire alarm, data, and controls are in this package.
An electrical takeoff is typically $150–$1,000 per estimate, varying by project size and scope, and most estimates are delivered in 24–48 hours.
Count luminaires by type, not as one EA bucket. Branch devices, equipment connections, and feeder raceway are different rows. A drawn route length is not conductor length: record conductor count, vertical rises, and terminations separately. The Excel sheet uses columns for tag, unit, sheet, and whether the item is base bid or an alternate. Temporary power is included only when the specifications put it in this contract.
These rows show how a commercial workbook can separate units. They are teaching lines, not a client bid and not a price.
| Line item | Unit or basis | Drawing reference | Review note |
|---|---|---|---|
| Luminaires by type | EA | Luminaire schedule | Keep emergency fixtures separate |
| Branch devices | EA | Power plan | Receptacles and disconnects are not one mix |
| Feeder raceway | LF | One-line and riser | Conductor count is a different column |
| Panels and gear | EA | Panel schedule | Tag each panel; do not lump gear |
A related teaching file is available: Electrical takeoff worksheet (illustrative). It is not a bid deliverable.
Reconcile the one-line diagram with panel schedules before counting branch devices. Keep fixtures by type, equipment connections by tag and feeders by conductor size and raceway. A drawn route length is not automatically the conductor length: record conductor count, vertical rises and termination allowances separately.
Confirm whether fire alarm, data, controls and temporary power belong to this package; their presence on a drawing does not establish electrical-contractor ownership.
Illustrative lighting count: 14 fixtures on Level 1 plus 11 on Level 2 equals 25 EA. Reconcile fixture types with the luminaire schedule; circuits, homeruns and controls require separate scope lines.
No. Scheduled fixtures, controls, raceway, and panels are separate lines. A teaching count of 14 fixtures on Level 1 plus 11 on Level 2 is 25 EA of fixtures only.
They belong in this package only when the drawings and specifications assign them to the electrical contractor. Presence on a sheet does not decide ownership.
Reconcile the one-line with the panel schedule before counting branch devices. Note AIC, voltage, and mounting when the schedule states them. Do not invent missing circuit data.
Inclusions, exclusions, and whether this trade is in your package are confirmed in the project quote. This page does not certify design or code compliance. PlanSwift and Bluebeam are named only as tools used in the industry.