Drawings to send
- Structural plans and details
- Foundation and slab schedules
- Concrete specifications
Send foundation plans, sections and slab details for a commercial concrete takeoff. The workbook separates concrete volume, form-contact area and reinforcement by element.

Send structural plans, sections, slab schedules, and say whether rebar is in this package or with the rebar trade.
Most estimates covering concrete are delivered in 24–48 hours at a fee typically between $150 and $1,000 per estimate, depending on project size and scope.
Convert thickness to feet, multiply length times width times thickness, and divide by 27 to get cubic yards. A 40 by 30 foot slab at 6 inches is 600 cubic feet, about 22.22 CY gross, before openings and thickened edges. Footings that overlap the slab are measured once, with the boundary stated. Formwork is contact square feet. Rebar is its own weight. Waste and order quantity are not the same as gross geometric volume. The Excel sheet keeps gross, deduction, and net in separate columns.
These rows show how a commercial workbook can separate units. They are teaching lines, not a client bid and not a price.
| Line item | Unit or basis | Drawing reference | Review note |
|---|---|---|---|
| Slab on grade | CY | Slab plan | Gross, deductions, net |
| Footings | CY | Foundation plan | Watch overlap with the slab |
| Form contact | SF | Sections | Not derived from CY |
| Reinforcement | LB or ton | Bar schedule | Separate from concrete volume |
A related teaching file is available: Concrete takeoff worksheet. It is not a bid deliverable.
Calculate concrete CY from element dimensions in feet divided by 27. Separate footings, walls, slabs and thickened edges; measure formwork by contact SF and reinforcement by its own unit. Reconcile overlapping slab and footing geometry.
Gross geometric volume, saved allowance-adjusted volume and order quantity are different values. Do not apply a second waste factor to an already adjusted sample quantity.
Illustrative slab: 40 ft x 30 ft x 0.5 ft = 600 cubic feet, or about 22.22 CY before deductions, thickened edges and waste.
No. It is gross geometric volume for that rectangle. Openings, edges, waste, and field conditions still have to be reviewed.
Only if the subcontract says the concrete price includes reinforcement. Otherwise rebar weight is a Division 03 companion line, not a hidden factor on the yards.
Measure them from the section and do not also leave them inside the slab rectangle if that would double the volume.
Inclusions, exclusions, and whether this trade is in your package are confirmed in the project quote. This page does not certify design or code compliance. PlanSwift and Bluebeam are named only as tools used in the industry.