Drawings to send
- Architectural floor plans
- Partition type and finish schedules
- Reflected ceiling plans
Commercial drywall follows the partition tag. Floor area does not become board area, and one face is not two faces.

Send partition plans, wall types, finish schedules, and reflected ceiling plans.
Most estimates for partitions and ceilings are delivered in 24–48 hours. Drywall fees are typically $150–$1,000 per estimate, by project size and scope.
A partition is length times height for each face and each layer. A 30 by 10 foot wall is 300 SF for one face. Board on both sides is 600 SF before openings and extra layers. Shaft walls, soffits, and ceilings are separate assemblies. Rated assemblies are taken from the wall type, not assumed. Acoustic insulation and finish level are exclusions or companion rows. The Excel sheet keys every row to the wall tag so a typical office bay is not copied onto a rated shaft.
These rows show how a commercial workbook can separate units. They are teaching lines, not a client bid and not a price.
| Line item | Unit or basis | Drawing reference | Review note |
|---|---|---|---|
| Partition, one face | SF | Wall tag on the plan | Length times height |
| Second face or extra layer | SF | Wall type | Only when the type calls for it |
| Ceiling board | SF | Reflected ceiling plan | Not equal to floor SF |
| Shaft or rated wall | SF | Rated wall type | Keep off the typical partition row |
Measure partitions by wall tag, height, face count and board layers. Keep shaft walls, soffits and ceilings separate; reconcile openings and finish levels to the architectural schedules.
Rated assembly requirements, acoustic insulation and deflection tracks must follow the specified assembly. Wall-face SF is not interchangeable with floor SF or board order quantity.
Illustrative partition: 30 ft x 10 ft = 300 SF of one wall face; double-sided board may require 600 SF before openings and layer counts.
When the measurement rule says to deduct openings. The opening size comes from the door schedule, and the deduction is visible.
Often they are together, but load-bearing framing and nonstructural studs can be different subcontractors. The request should say which one you want.
Reflected ceiling plans drive ceiling board. Do not multiply floor area by a factor and call it ceiling board.
Inclusions, exclusions, and whether this trade is in your package are confirmed in the project quote. This page does not certify design or code compliance. PlanSwift and Bluebeam are named only as tools used in the industry.